Ensure the installation team is ready for the installation and able to begin as soon as the truck arrives to avoid having it set up before the project can be completed and minimize idle time. Pre-mix bags usually range from $2.50 to $7, making them a cost-effective choice for small projects. One cubic yard is equal to the volume of a cube with edges that are one yard in length. Concrete delivery drivers do not pour concrete; they only deliver it.

A full truckload of concrete generally holds 10 cubic yards, while partially filled trucks or “short loads” cost $53 per cubic yard more, or about $172 per yard. Ready-mix is a no-brainer for mid-sized to large projects, but what about cost? If you use 60-pound bags, concrete for a patio this size ranges from $135 to $180. But you’ll need to rent a mixer, which adds another $40 to $60 per day. However, a fully loaded cement truck will hold 10 cubic yards—and partial “short” loads cost $15 to $20 extra for every cubic yard less than a full load. Most contractors plan the pouring of the wall panels in such a way that all the panels can be poured, albeit in stages, from outside the building.

Most companies require a minimum order of one cubic yard for delivery, plus a delivery surcharge. Be sure your site is prepared for the concrete delivery ahead of time, as some companies will charge for delays. In UK, a normal transit or RMC truck can carry 6m3 of concrete, but for few special project it can carry 8.5m3 to 10m3 of concrete. If you have a particularly large concrete job in the works, you may be better served by buying concrete by the ton.

Let’s cover three reasons why ready-mix is a much better option than hand mixing bags of concrete mix. When you’re pouring a large slab of concrete, sometimes skipping the bags and buying in bulk can save you a lot of money. And don’t let calculating cubic yards scare you –– it’s easy to determine how many cubic yards you’re going to need as long as you know the dimensions of your concrete slab. On average, homeowners pay $117 per cubic yard of concrete, with a typical cost range between $104 and $144 per cubic yard. But don’t start calculating your costs just yet –– there’s something you need to know about buying in bulk, and it’s called a short load fee. Calculate the concrete material needed to pour a slab, patio, footing, column, or post-fill-project in cubic yards or pre-mix bags, and estimate the cost of materials.

Special concrete finishes such as staining or stamped concrete costs from $2 to $18 per square foot to install depending on the intricacy of the design. Stamped concrete varies from a smooth polish to geometric patterns to something that resembles stone, brick, or tile. Stained concrete is cheaper, and one color is applied to the surface with a protective sealant.

A full 10-yard truckload with delivery costs $1,169 to $1,444, which is enough to pour a 20×24 driveway. In United State concrete measured in cubic yard, there are several sizes of RMC truck on road. Most common concrete truck has drum capacity of 11 to 15 cubic yards, however due to weight limit on the road they can carry 8 to 11 cubic yard of concrete. Buying by the truckload is typically sweeney’s pool service a total of 10 cubic yards, though this can vary from company to company. If you’re ordering less than a truckload of concrete, you’ll be charged a short load fee for running a concrete truck that’s partially empty. The average cost of concrete delivery is $119 to $147 per cubic yard for a full 10-yard truckload of ready-mix concrete, and $172 per yard for a short-load of less than 10 yards.

When hauling most materials, the weight of your load will be the limiting factor. For example, sand can weigh upwards of 3,000 pounds per cubic yard, meaning that in a massive, 30,000-pound dump truck, you could carry a maximum of 10 cubic yards. In a dump truck on a half-ton pickup frame, you could only carry a third of a yard of sand. A cubic yard represents a block of material that measures three feet on each side. In theory, the material itself can be anything, from water to stone to mulch. For this reason, yardage alone is an imperfect measurement of a dump truck’s overall capacity.